The following material was submitted to the New Mexico Environment Department (NMED) Drinking Water Bureau (DWB) on January 26, 2021.
- Application for Construction or Modification of a Public Water Supply System (3 pages, 1/26/2021)
- Application Checklist (1 page, 1/26/2021)
- Plans (73 11″ x 17″ pages, 24,475 KB, 1/7/2021)
- Specifications (322 8.5″ x 11″ pages, 6,053 KB, 1/7/2021)
- Engineering design summary, with material supporting adsorption treatment (95 8.5″ x 11″ pages, 7,959 KB, 10/1/2020)
- Disinfection plan (2 pages, 1/12/2021)
On 2/10/2021, Patrick Castillo at the NMED DWB sent Wilson & co. the following questions:
Engineering Review Comments
On 3/1/2021, Brian Ambrogi, Wilson & Company sent NMED his response to comments.
On 3/2/2021, the NMED DWB approved the application, issuing this Certificate of Project Approval.